Construction Update
Allhamdulillah with the grace and blessings of Allah. We started the new construction process and want to keep the community updated with what is going on .
Inshallah we will keep posting the pictures and videos on each stage of construction.
August 2021:
- General Contractor Selected
- Construction Contracts signed
- Preconstruction activities commenced
- The existing Mosque facility began to be evacuated
- Storage facility and logistics for the site are achieved
- Early enabling works commenced
September 2021:
- Secured all entrances
- Installation of Temporary Power
- Installation of site Fencing
- Installation of the temporary trailers
- Completion of the evacuation and move of all furniture items and storage
- Removal and disposal of all remaining furniture and other items needing disposal
- Commencement of the Selective Demolition of the facility
- Commencement of the Major Demolition of the MPR and main mussalah facilities
- Survey and Layout of the new mosque
- Major excavation for foundations
- Installation of the Infiltration Trench
- Landscaping removal of trees and relocation of Plants and Shrubs
- Inspection and repairs to the existing structure
- Submission of the plans and engineering to the City of Sammamish for the temporary prayer facilities trailers.
October 2021:
- Executed agreement with Sammamish Plateau Water District
- Commencement of work on the new facility Footing Foundation excavation, rebar and preparing to pour concrete
- Geotechnical surveys and inspections of subgrade
- Compaction and site preparation
- Forming of Footings
- Installations of Footings Rebar
- Footing inspection
- Concrete Pours for the Footings
- Stripping of the Footings
- Forming of Walls
November 2021:
- Wall Inspections
- Concrete Pours for the Walls
- Stripping the Wall Forms
- Completion of Structural Concrete
- Site civil activities
- Trench excavation for utilities
- Excavation for the water runoffs
- Construction of the Pony Walls
- Over framing of the Existing Floor
- Framing of the existing facility for the women’s prayer area and classrooms.
- Building of the Joist and Sheet Floor for the women’s prayer area and classrooms.